  • 08/19/10

Tower:

Completed floors 3-18, roof structures, stairs, elevators and windows. General cleanup and incidental work currently being performed.

Mall:

Completed floors 1, 2 and Atrium. Garage levels A,B,C completed with the exception of some minor work areas. General cleanup and incidental work currently being performed.

McCurdys:

Completed floors 1-6, basement, subbasement and roof. General cleanup and incidental work currently being performed.

Euclid:

Basement, floors 1, 3 and 4 are being abated. Floor 2 is being prepared for abatement.

Seneca:

Completed

B Forman:

Completed

Work Force Update:

The current work force this week is at 106.


  • 08/05/10

Tower:
Completed floors 3-18. Roof structures, stairs, elevators and windows are being abated.
Mall:
Floors 1, 2, atrium completed with the exception of some minor work areas. Garage levels A,B,C completed with the exception of some minor work areas.
McCurdy's:
Completed Floors 2-6, basement and subbasement. Floor 1 and roof abatement is underway.
Euclid:
Floors 3 and 4 are being abated. Floors 2, 1 and basement are being prepared for abatement.
Seneca:

Completed.

B Forman:

Completed.
Work Force Update:
The current work force this week is at 109.


  • 07/29/10

Tower:
Abatement completed on floors 3-18. Roof structures, stairs, elevators and Windows are being abated.
Mall:
Floors 1, 2, atrium completed with the exception of some minor work areas.
Garage levels A,B,C completed with the exception of some minor work areas.
McCurdy's:
Completed floors 2-6, basement and subbasement. Floor 1 abatement is underway.
Euclid:
Floors 3 and 4 are being abated. Floors 2, 1 and basement are being prepared for abatement.
Seneca:

Completed.

B Forman:

Completed.

Work Force Update:
The current work force this week is at 107.

  • 07/22/10
    Tower:
    Completed floors 4-17.
    3rd floor, roof structures and windows are being abated.
    Mall:
    2nd floor completed with the exception of some minor work areas.
    Mall atrium scaffold is taken down.
    1st Floor completed with exception of the former Wegmans loading dock and some minor work areas.
    McCurdys:
    Completed floors 2-6, basement and subbasement. Floor 1 abatement is underway.
    Euclid:
    Floors 3 and 4 are being abated. Floors 2 and 1 are being prepared for abatement.
    Seneca:

    Completed.
    B Forman:
    Completed.
    Work Force Update:
    The current work force this week is at 112.
  • 7/15/10
    Tower:
    Completed floors 4-17.
    3rd floor, roof structures and windows are being abated.
    Mall:
    2nd floor completed with the exception of some minor work areas.
    Mall atrium abatement is completed, scaffold being taken down.
    1st floor completed with exception of the south end and some minor work areas.
    McCurdys:
    Completed floors 2-6, basement and subbasement. Floor 1 abatement is underway.
    Euclid:
    Floors 3 and 4 are being abated.
    Seneca:
    Completed.
    B Forman
    Completed.
    Work Force Update:
    The current work force this week is at 106.
 
  • 7/8/10
    Tower:
    Completed floors 4-17.
    3rd floor, rfoof structures and windows are being abated.
    Mall:
    2nd floor completed with the exception of overhead beam
    Mall atrium abatement is completed, scaffold being taken down.
    1st floor completed with exception of the south end and some minor work areas.
    McCurdys:
    Completed floors 2-6 and subbasement. Floor 1 and Basement abatement is underway.
    Euclid:
    Floors 3 and 4 are under containment.
    Seneca:
    Completed.
    B Forman:
    Completed.
    Work Force Update:
    The current work force this week is at 105.
 
  • 7/1/10
    Tower:
    Completed floors 4-17.
    3rd floor, Roof Structures and Windows are being abated.
    Mall:
    2nd floor completed with the exception of overhead beam and south wall abatement.
    Mall atrium abatement is completed, scaffold being torn down.
    1st floor completed with exception of the south end and some minor work areas.
    McCurdys:
    Completed floors 2-6 and subbasement. Floor 1 and basement abatement is underway.
    Euclid:
    Floors 3 and 4 are under containment.
    Seneca:
    Completed Floors 1-7, basement, roof and windows. Final cleanup and incidental work being completed.
    B Forman:
    Completed floors 1-6, basement and roof.
    Final cleanup and incident work being completed.
    Work Force Update:
    The current work force this week is at 111.
 
  • 6/24/10
    Tower:
    Completed floors 4-17.
    3rd floor, roof structures and windows are being abated.
    Mall:
    2nd floor completed with the exception of overhead beam and south wall abatement.
    Mall atrium abatement is completed, scaffold being taken down.
    1st floor completed with exception of the south end and some minor work areas.
    McCurdys:
    completed floors 2-6, subbasement. Floor 1 and basement – abatement is underway.
    Euclid:
    Floors 3 and 4 are under containment.
    Seneca:
    Completed Floors 1-7, basement, roof and windows. Final cleanup and incidental work being completed.
    B Forman:
    Completed floors 1-6, basement and roof.
    Final cleanup and incidental work being completed.
    Work Force Update:
    The current work force this week is at 118.
  • 06/17/10

Tower:
Completed Floors 17, 16, 15, 14, 13, 12, 11, 10, 9, 8, 7, 6, 5, 4.
3rd floor and Windows are being abated.
Mall:
2nd Floor completed with the exception of overhead beam and south wall abatement.
Mall Atrium abatement is completed, scaffold being torn down.
1st Floor hallway abatement continues.
McCurdy's:
Completed Floors 6, 5, 4. 3, 2 and subbasement. Floor 1 and Basement abatement is underway.
Euclid:
Soft Demolition continues.
Seneca:

Completed Floors 7, 6, 5, 4, 3, 2, 1, basement and roof. Abatement of windows on South Clinton Avenue is completed. Final Cleanup and incidental work being completed.

B Forman:

Completed Floors 6, 5, 4, 3, 2, 1, basement and roof.
Final cleanup and incident work being completed.
Work Force Update:
The current work force this week is at 130.


  • 06/10/10

Tower:
Completed Floors 17, 16, 15, 14, 13, 12, 11, 10, 9, 8, 7, 6, 5, 4.
3rd floor is being abated.
Mall:
2nd Floor completed with the exception of overhead beam and south wall abatement.
Mall Atrium abatement is completed.
1st Floor hallway abatement continues.
McCurdy's:
Completed Floors 6, 5, 4. 3, 2 and subbasement. Floor 1 and Basement – abatement is underway.
Euclid:
Soft Demolition has begun.
Seneca:

Completed Floors 7, 6, 5, 4, 3, 2, 1, basement and roof. Abatement of windows on South Clinton Avenue continues. Final Cleanup and incidental work being completed

B Forman:

Completed Floors 6, 5, 4, 3, 2, 1, basement and roof.
Final cleanup and incident work being completed.

Work Force Update:
The current work force this week is at 140.


  • 06/03/10

Tower:
Completed Floors 17, 16, 15, 14, 13, 12, 11, 10, 9, 8, 7, 6, 5, 4.
3rd floor is being prepared for abatement
Mall:
2nd Floor completed with the exception of overhead beam and south wall abatement
Mall Atrium abatement continues.
1st Floor hallway abatement continues.
McCurdy's:
Completed Floors 6, 5, 4. 3, 2 and subbasement. Floor 1 and Basement abatement is underway.
Euclid:
Scheduled to start when other areas are complete.
Seneca:

Completed Floors 7, 6, 5, 4, 3, 2, 1, basement and roof. Abatement of windows on South Clinton Avenue continues. Final Cleanup and incidental work being completed

B Forman:

Completed Floors 6, 5, 4, 3, 2, 1, basement and roof.
Final cleanup and incident work being completed.

Work Force Update:
The current work force this week is at 141.


  • 05/20/10

Tower:
Completed Floors 17, 16, 15, 14, 13, 12, 11, 10, 9, 8, 7, 6, 5, 4.
3rd floor is being prepared for abatement.
Mall:
2nd Floor: Containment (7) Abatement continues. Mastic Removal.
Mall Atrium abatement continues.
1st Floor: Mall hallway abatement continues.
McCurdy's:
Completed Floors 6, 5, 4. 3, 2 and Subbasement. Floor 1 and Basement: abatement is underway.
Euclid:
Scheduled to start when other areas are complete.
Seneca:

Completed Floors 7, 6, 5, 4, 3, 2, 1, basement and roof. Abatement of Windows on South Clinton Avenue are left to abate. Final Cleanup and incidental work being completed.

B Forman:

Completed Floors 6, 5, 4, 3, 2, 1, basement and roof.
Final cleanup and incident work being completed.

Work Force Update:

The current work force this week is at 129.


  • 05/13/10

Tower:
Completed Floors 17, 16, 15, 14, 13, 12, 11, 10, 9, 8, 7, 6, 5, 4.
3rd floor is being prepared for abatement.
Mall:
2nd Floor: Containment (7) Abatement continues. Mastic Removal.
Scaffold for Mall Atrium is constructed, abatement has begun.
1st Floor: Mall hallway abatement continues.
McCurdy's:
Completed Floors 6, 5, 4. 3, 2 and Subbasement. Floor 1 and Basement preparation and abatement is underway.
Euclid:
Scheduled to start when other areas are complete.
Seneca:

Completed Floors 7, 6, 5, 4, 3, 2, 1, basement and roof. Windows on South Clinton Avenue are left to abate. Final Cleanup and incidental work being completed

B Forman:

Completed Floors 6, 5, 4, 3, 2, 1, basement and roof.
Abatement is completed on roof. Final cleanup and incident work being completed.

Work Force Update:
The current work force this week is at 143.


  • 05/07/10
Tower:

Completed Floors 17, 16, 15, 14, 13, 12, 11, 10, 9, 8, 7, 6, 5, 4.

3rd floor is being prepared for abatment. 

Mall:

2nd Floor is completed, with the exception of:

Containment (7) Abatement continues, scraping.

Scaffold for Mall Atrium is constructed. Preparation work for abatement continues.   1st Floor Containment 2 (West Side) completed.  Mall hallway abatement begins. 

McCurdy's:

Completed Floors 6, 5, 4. 3 and Subbasement.  Floor 2 Abatement is nearly completed. Floor 1 and Basement preparation and abatement is underway.  

Euclid:

Scheduled to start when other areas are complete.

Seneca:

Completed Floors 7, 6, 5, 4, 3, 2, 1, basement and roof.  Windows on South Clinton Avenue are left to abate.

B Forman:

Completed Floors 6, 5, 4, 3, 2, 1, basement and roof.  

Abatement is completed on roof.

Work Force Update:

The current work force this week is at 133.  


  • 04/23/10

Tower:
Completed Floors 17, 16, 15, 14, 13, 12, 11, 10, 9, 8, 7, 6, 5, 4.
3rd floor is on hold until other work is completed.
Mall:
2nd Floor is completed, with the exception of:
Containment (7) Abatement has begun, ceiling demo.
Scaffold for Mall Atrium is constructed, will continue once other work is completed.
1st Floor Containment 2 (West Side) final clean. Mall hallway abatement has begun.
McCurdy's:
Completed Floors 6, 5, 4. 3 and Subbasement. Floor 2 Abatement continues. Floor 1 and Basement preparation and abatement is underway.
Euclid:
Scheduled to start when other areas are complete.
Seneca:

Completed Floors 7, 6, 5, 4, 3,2 and basement. Finishing abatement on Floor 1, Window and roof abatement is current.

B Forman:

Completed Floors 6, 5, 4, 3, 2, 1, and basement .
Abatement is ongoing, roof materials.

Work Force Update:
The current work force this week is at 156.


  • 4/09/10

Tower:
Completed Floors 17, 16, 15, 14, 13, 12, 11, 10, 9, 8, 7, 6, 5, 4.
3rd floor is on hold until other work is completed.
Mall:
2nd Floor is completed, with the exception of:
Containment (7) Containment preparation continues.
Scaffold for Mall Atrium is constructed. Will continue once other work is completed.
1st Floor Containment 1 (East Side) visual inspection today. Containment 2 (West Side) Power Washing.
McCurdy's:
Completed Floors 6, 5, 4. 3 and Subbasement. Floor 2 Abatement continues. Floor 1 and Basement preparation and abatement is underway.
Euclid:
Scheduled to start when other areas are complete.
Seneca:
Completed Floors 7, 6, 5, 4, 3 and 2. Abatement on Floor 1 and basement has begun.

B Forman:
Completed Floors 6, 5, 4, and 3.
Abatement is ongoing - Floors 1 and 2 and basement.
Work Force Update:
The current work force this week is at 184.

  • 03/03/10

Midtown Rising Project update presentation given by Thomas Richards

  • 2/25/10

Tower:
Abatement completed on floors – 17, 16, 15, 14, 13, 12, 11, 10, 9, 8, 7, 6, 4

3rd and 5th floors are being prepared
Mall:
2nd Floor abatement is completed with the exception of:

Containment 7 will be completed after most of 1st Floor is completed
Scaffold for Mall Atrium is constructed – Containment 1 is being prepared
Continue abatement in Containment 1 – 1st Floor, East Side.
McCurdys:

5th Floor- completing the last minor containment. 4th Floor - completing the last minor containment. 3rd Floor - fireproofing removal continued. Abatement has started on the 2nd Floor. Abatement in subbasement continues – 1 large work area is currently under containment.
Euclid:
Scheduled to start in March.
Seneca:
Floors 4, 6 and 7 – completed. Floors 2, 3, and 5 – ceiling system removal continue under abatement.

B Forman:
Abatement is ongoing 4th Floor. Soft demolition is ongoing on the 3rd Floor.

Work Force Update:

The current work force this week is at 216.


  • 01/28/10

Tower:
Completed floors 17, 16, 15, 14, 13, 12, 10 and 9. Mastic removal completed on floor 11. Abatement continues floors 6, 7 and 8 – power washing.
Mall:
All 2nd Floor work: Containment 5 – Final cleaning. Containment 6 – Fireproof removal. Scaffold for Mall Atrium is 50% constructed.
McCurdy's:
Abatement is completed 6th floor. 5th floor completing the last minor containments. 4th floor abatement continues. Preparation in subbasement.
Euclid:
On hold until a crew becomes available.
Seneca:

6th / 7th floor – Visual inspection within a week. 4th floor – Scrape removal of fire proofing. Preparation of 2nd floor containment.

B Forman:

Abatement completed on floors 6 and 5. Abatement has started 4th floor.

Work Force Update:
The current work force this week is at 220.

  • 01/21/10

Tower:
Completed abatement on floors 17, 16, 15, 14, 13, 12, 10 and 9. Mastic Removal took place on floor 11. Abatement continues floors 6, 7 and 8 with the scrape removal of Fire Proofing.
Mall:
All 2nd Floor work:
Containment 3 - Passed visual inspection and clearance air sampling.
Containment 4 - Passed visual inspection and clearance air sampling.
Containment 5 - Final Cleaning.
Containment 6 - Abatement Preparation.
McCurdy's:
Abatement continues on the 6th and 5th floors with the last minor containments on both floors underway. 4th Floor abatement continues.
Euclid:
On hold until a crew becomes available.
Seneca:

7th Floor - Final cleaning. 6th Floor - Final Cleaning. 4th Floor - Scrape removal of Fire Proofing.

B Forman:

Subcontractor continues soft demolition throughout the building. Abatement continues on Floors 6 and 5.

Work Force Update:
The current work force this week is at 225.


  • 01/14/10

Tower:
Completed floors: 17, 16, 15, 14, 13, 12, 10 and 9. Mastic removal crew to start floor 11 soon. Abatement continues on the ceiling systems of floors 6, 7 and 8.
Mall:
Containment 2 passed visual inspection and clearance air sampling. Containment 3 underwent final cleaning. Containment 4 undergoing mastic removal.
McCurdy's:
Abatement continues on the floors 5 and 6 with the last minor containments on both floors underway, Fourth floor abatement has begun.
Euclid:
On hold until a crew becomes available.
Seneca:
7th Floor: Final cleaning. 6th Floor: Fire proof removal. 4th Floor: Above ceiling demolition.

B Forman:
Subcontractor continues soft demolition throughout the building. Abatement has begun on Floors 6 and 5.

Workforce Update:
The current work force this week is at 240.


  • 12/18/09

Tower: Abatement is completed on floors 17, 16, 15, 14, 13, 12, 10 and 9. Abatement is taking place on floor 11. Preparation for abatement has begun floors 6, 7 and 8.
Mall: Abatement in the southwest corner second floor (containment 1) is completed. Final cleaning is current; visual inspection is scheduled for next week. Mastic removal has begun in the southeast corner second floor (containment 2). Mastic removal will start on the east side (containment 3) when containment 2 is completed. Containment 4, west side second floor is under abatement; currently above ceiling demolition. Demolition of Mall non-structural elements continues.
McCurdy's:
Abatement continues on the sixth and fifth floors.
Euclid: On hold until a crew becomes available.
Seneca: Abatement continues on floors 6 and 7.
B Forman: Subcontractor continues soft demolition. Abatement is completed on floors three and four.
Workforce Update: The current workforce is at 204.


  • 12/11/09

Tower: Abatement completed on Floors 12, 13, and 14. Abatement continues on Floors 9 and 10, with final cleaning procedures currently being performed. Mobilizing to abate floors 6, 7, 8 and 11.
Mall: Abatement in the southwest is in the final phase, with floor tile mastic removal. Abatement in the southeast continues with removal of floor tile. Abatement continues in the east side, with fireproof removal. Demolition of Mall non-structural elements continues.
McCurdy's: Abatement continues on the 6th Floor, with a partial visual inspection pending, along with other areas being prepared for abatement on the 5th Floor.
Euclid: Loading out soft demolition debris continues in various areas of the building.
Seneca: Abatement continues on Floors 6 and 7.
B Forman: Subcontractor has begun soft demolition on all floors.


  • 12/04/09

Tower: Abatement continued on Floors 12, 13, and 14, visual inspection pending. Abatement continues in Floors 9 and 10, with floor tile mastic removal.
Mall: Abatement in the southwest is in the final phase, with floor tile mastic removal. Abatement in the southeast continues with removal of floor tile. Abatement continues in the east side, with fireproof removal. Demolition of Mall non-structural elements continues.
McCurdy's: Abatement continues on the 6th Floor, with a partial visual inspection pending, along with other areas being prepared for abatement on the 5th Floor.
Euclid: Loading out soft demolition debris continues in various areas of the building.
Seneca: Abatement continues on Floors 6 and 7.

B Forman: Subcontractor has begun soft demolition on all floors.


  • 11/17/09

Tower: Abatement work continued on Floors 12, 13, and 14, and is in the final phase. Abatement has begun on Floors 8, 9 and 10.
Mall: Abatement in the southwest is in the final phase. Abatement in the southeast continues with removal of fireproofing. Abatement is underway for abatement in the east side. Demolition of Mall non-structural elements continues.
McCurdy's: Abatement continues on the 6th Floor with removal of fireproofing.
Euclid: Loading out soft demolition debris continues in various areas of the building.
Seneca: Abatement has begun on Floors 6 and 7.

B Forman: Subcontractor has begun removing movable objects from the building for disposal.

  • 11/9/09:

Tower: Abatement continued on Floors 12,13, and 14 and is close to completion. Abatement work has started on Floors 15,16, and 17. Preparation has started on Floors 8, 9 and 10.
Mall: Abatement in the southwest corner continues and is close to completion. Abatement in the southeast continues with ceiling and above ceiling demolition, with extensive restaurant infrastructure being taken out. Demolition of Mall non-structural elements continued.
McCurdy's: Preparation work for abatement has started on the 6th Floor.
Euclid: Loading out soft demolition debris continues in various areas of the building.
Seneca: Abatement preparation has started on Floors 6 and 7.

B Forman: Subcontractor has begun preliminary work and will be mobilizing within the 2 weeks.


  • 11/3/09:

Installation of construction fencing around perimeter of site begins.

  • 11/2/09:

Tower: Abatement continues on floors 12,13, and 14. Cleaning of residual fireproofing and removal of floor tiles continues. Work areas are being prepard on on floors 15, 16, and 17.
Mall: Abatement in the southwest corner continues, with washing procedures ongoing. Abatement in the southeast corner started with ceiling demolition to access the asbestos fireproofing. Demolition of Mall non-structural elements continued.
McCurdy's: Loading out soft demolition debris is ongoing in various areas of the building.
Euclid: Loading out soft demolition debris is ongoing in various areas of the building.
Seneca: Sub-contractor Marcor has mobilized and begun interior strip-out of movable objects.

B Forman: Electrical and mechanical preparations are being made for abatement. Subcontractor will be mobilizing next week.

Work Force Update: The current work force is at 121. Continued increases in the workforce are expected throughout the coming weeks and months.


  • 10/23/09:

Tower: Abatement continued on floors 12,13 and 14 with bulk removal of asbestos fireproofing completed and continued cleaning of residual fireproofing. Preparation of floors 15, 16 and 17 for abatement has begun with construction of asbestos abatement containments.
Mall: Abatement in the southwest corner began on October 19, 2009 with the removal of asbestos fireproofing, pipe insulation and fittings. Preparation continues for abatement with containment construction in the southeast. Interior demolition of Mall’s decorative structures has started.
McCurdy's:
Soft demolition activities are ongoing in various areas of the building, including the basement. Major soft demolition activities have been completed on floors 1- 6. A debris chute installation has begun.

Euclid: Soft demolition activities continue throughout the building.
Work Force Update: The current work force is at 113. Continued increases in the workforce are expected throughout the coming weeks and months.
Sub contractors: Royal Environmental of Rochester will mobilize to the site within the next week.

  • 10/13/09:

Tower: Abatement work consisting of asbestos fireproofing removal is ongoing on floors 12, 13 and 14. Soft demolition activities are completed, with the exception of floors 3, 18 and 19.

Mall: Major soft demolition activities are completed in the mall areas. The installation of hard walls for future containment work areas is ongoing. Abatement work area construction has started in the southeast and southwest corners.

McCurdy's: Soft demolition activities are completed from floors 6 to 3, with ongoing work on the 2nd floor.

Euclid Building: Electrical work, which consists of de-energizing the building and installing temporary power, is currently being performed to prepare the building for abatement.

Work Force: The current work force is at 113 personnel. Cambria and their subcontractors will be adding significant staffing in the coming weeks.

Subcontractors: Marcor Environmental has begun mobilizing to the site and Royal Environmental will be doing the same in the coming weeks. Both Royal and Marcor have Rochester Offices and will employ local labor.


  • 10/1/09:

Tower: Abatement work consisting of ceiling system removal continued on floors 12, 13 and 14. Soft demolition activities were completed down to the 5th floor. Soft demolition activities are continuing on the fourth floor.

Mall: Soft demolition activities are ongoing. Mall areas are being prepared for abatement by installing partitions to isolate future abatement work areas.

McCurdy’s: Soft demolition activities on the 6th floor have been completed and are currently ongoing on floors 4 and 5. The removal of non-fixed items and debris in the basement areas has been completed.

Euclid Building: The removal of non-fixed items, debris and universal wastes (i.e. paints, cleaning solutions, electrical components) has been initiated.

Work Force: The current work force is at 99 personnel. Cambria and their subcontractors will be adding significant staffing in the coming weeks.

Subcontractors: Cambria Contracting has reached an agreement with two additional abatement subcontractors, Marcor Environmental and Royal Environmental, both have Rochester Offices and will employ local labor.

  • 09/24/09 - Work in the tower included the continuation of asbestos abatement activities on floors 12,13 and 14. Work on these floors included the removal of ceiling systems and plaster walls to access abatement areas. Interior soft demolition and construction and demolition debris removal continued on the other floors of the tower and mall. Cambria also had its elevator repair subcontractor on-site to load test and repair elevators for debris removal operations. In the McCurdy’s Building, Cambria’s subcontractor continued the removal of non-fixed building components and construction debris. Electrical system modifications were also made within the McCurdy’s Building to prepare for upcoming abatement work.
  • 09/18/09 - Cambria established containment of floors 12,13 and 14 and started abatement activities on the 14th floor. The abatement work included the removal of the ceiling system on the entire 14th floor. Ongoing work in the tower included soft demolition activities on the lower floors. Soft demolition and non-asbestos waste removal continued in the Mall area. Significant progress was also made in clearing out non-fixed building components (i.e. cabinets, display cases, fixtures) from the McCurdy’s Building.
  • 09/10/09 - Construction of the perimeter fence will begin in approximately two weeks, and the Main & Clinton bus stop will be moved across the street (the Main & Clinton bus stop for Clinton Avenue busses heading north will be moved from the southeast corner to the northeast corner of Main & Clinton). Abatement of McCurdy's and Seneca is about three weeks away as each contractor must develop abatement plans and submit various required documentations. There are approximately 74 workers on site, including 32 from Laborer's Local 435 (inclusive of 4 apprentices). The project construction manager, LiRo Engineers, has established an office at 45 East Avenue. Their office is open M-F, 9-5 and phone is (585)232-3552. Clarification from previous update: DOL asbestos notification date was Sept 4, but actual asbestos abatement activities on floors 12-14 won't commence until Sept 11, 2009.
  • 09/02/09 - Cambria Contracting Inc. will begin asbestos abatement work on floors 12, 13 and 14 of the Midtown Tower on Friday, Sept. 4. These areas represent an isolated portion of the building which will not impact the public. A community briefing on the abatement process will be held in the near future before work proceeds to the common areas of the project. Other preparation progress at the site so far includes demolition and debris removal from the B. Forman Building, as well as at other interior stores in the plaza. In addition, the restaurant and bar areas on the Tower's 14th floor have been gutted and project headquarters have been established at 45 Euclid St.Cambria has selected two subcontractors to perform abatement work on the Seneca and McCurdy buildings, Rochester-based Marcor Remediation, Inc. and Bristol Environmental Inc. out of Bristol, PA. A minimum of fifty percent of the workers (including workers from all subcontractors) are required to be local hires, either through the Laborer's Local 435 or job interviews conducted at the project headquarters site.